The completion of Autoroute 30

Schedule

Western Section

Preliminary study: Fall 2004
Acquisitions: 2003-2009
PPP process: 2005-2008
Construction using a conventional method: starting in 2006
Construction using the PPP method: starting in 2009

Scheduled to open to traffic in late 2012

Eastern Section

Final study: 2004-2005
Acquisitions: 2005-2009
Plans and specifications: 2004-2007
Construction: starting in 2005

Opened to traffic since November 19th 2010

Jean-Leman Segment in the Eastern Section

Final study: 2007
Acquisitions: 2007-2010
Plans and specifications: 2007-2009
Construction: starting in 2009

Opened to traffic since November 7th 2011